SightInsights - Integrate schedules with our progress tracking
Schedule Integrations
You can now import schedules from Primavera P6 & Microsoft Project to your CupixWorks SightInsights enabled projects.
- Import .XER, .XML schedule files.
- Manually link schedule activity IDs to BIM objects to track installation progress against the forecasted dates.
- If BIM includes Activity IDs, then the BIM & Schedule activities will be automatically linked to each other.
- After initial configuration, when you import an new version of the schedule we will detect changes and update the Task name, Start, & End Date for all affected BIM objects.
- Export SightInsights data to update your schedule or company dashboard with field confirmed installation statuses.
CupixWorks SightInsights now combines field verified installation data with your scheduling software!
Create and track progress of vendors
When tracking installation progress you can now filter by subcontractors with a new user Group type called 'Vendor.' In addition to tracking volume and percentage of all completed work for a project, you can now track volume and percentage per subcontractor as 'Vendor'.
Contact your CSM to get started today!